Timeline of the Edwards Dam & Kennebec River Restoration
1834 |
Maine citizens, fearing decimation of fisheries populations, protest against the concept of a dam in Augusta when it is first proposed in legislative authorization several years before the dam is even built. |
1837 |
Kennebec River Dam Co. builds dam below the head of tide in Augusta. Construction includes locks for boat passage and fish ladder. Operator changes name to Kennebec Locks & Canal Company. |
1838 |
Fish ladder washed away in spring flood. Dam’s owners refuse to rebuild fish passage. |
1842-1846 |
Dam provides power for seven saw mills, a grist mill, and a machine shop. |
1868 |
Saw mill and grist mill destroyed by fire. |
1870 |
Major breach of dam. Dam rebuilt to current configuration. |
1882 |
Ownership changes to Edwards Manufacturing Company. Large textile mill employing 700+ workers built on west shore. Dam provides mechanical power for the textile mill. |
1903 |
Eight water wheels in operation provide mechanical power by means of shafts, pulley, and belts. |
1913 |
First electrical generators installed. |
1973 |
Bates Manufacturing sells its Edwards Division to Miller Industries, saving 800 area jobs. Edwards’ name goes with sale. |
1974 |
150 feet of dam washes out in winter flood. |
1975 |
Dam repaired despite pleas from fisheries biologists to allow the river to flow free. |
Early 1980s |
Textile mill ceases operation. All workers laid off. |
1984 |
Edwards Manufacturing Co. signs 15-year contract to sell electricity at approximately three times the market price to Central Maine Power. |
1986 |
Maine Department of Marine Resources initiates fisheries restoration for alewife in the Kennebec River. |
1987 |
|
1988 |
Edwards installs experimental fish pump to assist KHDG fisheries restoration effort. |
1989 |
|
1990 |
Hydro generation equipment rebuilt following fire. Remains of mill buildings demolished. |
1991 |
|
1992 |
City of Augusta becomes co-licensee with Edwards Manufacturing Company with a contract that provides 3% of gross revenues to the city. |
1993 |
|
1994 |
FERC issues new policy concluding it has authority to deny an application for relicensing as well as authority to order a dam removed at the dam owner’s expense. Edwards and Augusta object. |
1995 |
Edwards/Augusta withdraw their proposed 11.5-megawatt expansion and amend their application to maintain status quo electrical capacity. |
1996 |
|
1997 |
|
1998 |
|
1999 |
|
2000 |
|
2006 |
|
2007 |
|
2008 |
|
2009 |
|
2011 |
Nearly three million alewives pass the Benton Falls lift. |
2014 |
The Maine Department of Inland Fisheries & Wildlife counts 58 Bald Eagles in one day (June 6) in a 5-mile stretch of the Sebasticook River. This likely is the largest gathering of Bald Eagles in the Northeast and possible anywhere north of the Chesapeake. |
2018 |
More than five million alewives passed the Benton Falls lift, which makes this alewife run the largest in the entire United States. |
2019 |
NRCM and others gathered on the banks of the Kennebec River to celebrate the 20th anniversary of the removal of the Edwards Dam, and announced plans to create an educational display at the dam site. |
2024 |
NRCM continues its work to restore the Kennebec River, focusing on four dams on the river between Waterville and Skowhegan. Learn more about that work and how you can get involved. |