In April 2023, a Cumberland County jury ruled in CMP’s favor during a court case that very likely will decide the future of the company’s controversial transmission corridor. The decision was based on technical legal issues and not on the merits of whether or not this was a good project for Maine
We are disappointed with the outcome and remain sharply focused on achieving a just and equitable clean energy future that works for all Mainers.
Maine has already shown there’s a better path forward than the CMP corridor. A path focused on regional collaboration and centered in Maine’s pragmatic approach to solving problems.
Mainers are pursuing home-grown clean energy sources, like the King Pine wind project in Aroostook County that will deliver new and verifiable reductions in pollution rather than a shell game that shifts existing energy for maximum profit.
Maine voters got it right when they overwhelmingly passed a referendum rejecting the CMP corridor because it’s a bad deal for Maine and a bad deal for our climate.
NRCM is honored to stand with youth climate justice activists, tribes in Maine and Canada, people across western Maine who rely on a vibrant outdoor recreation economy, and many others in opposing the CMP corridor. Thank you to everyone who partnered with us on this hard-fought campaign.
What is the CMP Corridor?
Central Maine Power (CMP) proposed building a 145-mile transmission line through the heart of Maine to send hydropower from Quebec to electricity customers in Massachusetts.
The CMP corridor is a bad deal for Maine. It would permanently damage undeveloped forest and wildlife habitat, stifle the local renewable energy industry, and jeopardize the creation of clean energy jobs. The corridor won’t reduce global greenhouse gas emissions or create sustainable jobs for Maine people.
Top 4 Reasons NRCM Opposes the Corridor:
- Won’t reduce climate-changing pollution, and may actually increase it.
- Cuts 53 miles of new transmission lines through undeveloped forests in Maine’s North Woods, harming brook trout, deer, other wildlife, and the tourism economy.
- Jeopardizes the construction of new in-state renewable energy projects and creation of clean energy jobs.
- Generates billions of dollars of profit for CMP and Hydro-Quebec while offering very little to Maine people and businesses.
Watch our webinars to learn more about the CMP transmission line:
- View a recording of our webinar featuring Mainers speaking about why they supported Yes on 1
- CMP Corridor: Bad for Maine's Forests & Wildlife
- NRCM experts on why the CMP corridor is a bad deal for Maine
- Western Maine residents and renewable energy advocates on how CMP is putting profits over Maine people
Why the CMP Transmission Line is Bad for Maine’s Forests and Wildlife
CMP’s proposal would cut 53 miles of new line through undeveloped parts of Maine’s North Woods. The damage would fragment the largest contiguous temperate forest in North America and perhaps the world.
- This destruction would clear trees and plants through 263 wetlands, across 115 streams, and near remote Beattie Pond.
- It would harm Maine’s deer herd by blocking access to deer winter shelter and feeding areas.
- It would cut right through the heart of Maine’s brook trout habitat, including areas where public agencies and private citizens have spent millions to protect brook trout.
Majority of Mainers Oppose CMP's Corridor
The vast majority of Maine voters are firmly opposed to CMP proposal, according to a statewide poll. The opposition from Mainers is widespread and growing, especially in Western Maine where the transmission line would be located.
- In a stunning rebuke to CMP’s proposal, 25 towns have voted to oppose or rescind their support for the project.
- Two major unions and the Sportsman’s Alliance of Maine are also opposed to the project.
- The Maine State Federation of Firefighters has expressed concern about the risk of fires.
- In February 2021, Maine Secretary of State Shenna Bellows certified that more than enough valid signatures had been gathered to place a citizens referendum on the November 2021 ballot opposing the CMP corridor.
25 Maine towns rescinded their support or came out in opposition to the proposed transmission line:
- Alna (rescinded letter of support)
- Anson (town residents voted (98-12) to oppose the project)
- Caratunk (rescinded letter of support)
- Chesterville (town residents voted to oppose the project)
- Dennistown (wrote letter in opposition to project)
- Durham (rescinded letter of support and town residents voted to oppose by 190-8 vote)
- Embden (town residents voted 50-10 to oppose after Select Board had rescinded its support)
- Eustis (town residents voted to oppose the project by a vote of 103-4 )
- Farmington (town residents voted to rescind support and oppose the project)
- Greenville (town residents voted (290-58) to oppose the project)
- Industry (Select Board and town residents rescind support and oppose the project)
- Jackman (town residents voted to oppose)
- Jay (town residents voted to oppose)
- Livermore Falls (town residents voted (43-5) to oppose)
- Moose River (town residents voted to oppose)
- Moscow (town residents voted (35-9) to oppose)
- New Sharon (town residents voted (82-4) to oppose the project)
- Pownal (rescinded letter of support and town voted (76-27) to oppose project)
- Rome (town residents voted (27-2) to oppose project)
- Starks (town residents rejected motion to support project)
- The Forks (town residents voted to oppose)
- West Forks (town residents voted to oppose)
- Wilton (town residents voted (162-1) to rescind support and oppose the project)
- Wiscasset (rescinded letter of support)
- Woolwich (town residents voted to rescind support (611-158) and to formally oppose (585-176)
Organizations that Opposed or Rescinded Support:
- Androscoggin County Commissioners voted to rescind support
- Franklin County Commissioners voted to rescind support
- Sportsman's Alliance of Maine has rescinded its support
- United Steelworker's Maine Labor Council voted to oppose project
- Bath Iron Works' largest union, the International Association of Machinists and Aerospace Workers Local S6 opposes
- Upper Enchanted Owners Road Association voted 23-0 against the CMP corridor
Why the CMP Transmission Line is Bad for Our Climate
Read our blog post explaining why the CMP corridor is a bad deal for Maine and for the climate.
CMP’s proposal was not about climate. It was about making CMP more money—a shell game to sell existing hydropower to Massachusetts because they’ve agreed to pay more for it.
CMP’s line would do nothing to reduce climate-changing pollution because there is no assurance it will result in new renewable energy being created.
- Read the analysis conducted by environmental and renewable energy groups that concluded that the CMP corridor would not reduce carbon pollution and therefore would have no benefit for climate change.
- Read about the concerns raised by the Massachusetts Attorney General's Office that CMP's power line would not reduce greenhouse gases.
- Read or listen to NRCM’s testimony in support of LD 640, which would have required an independent climate impact study for the project
CMP’s transmission line could make it harder for local renewable energy projects to move forward, costing Maine new clean energy jobs and stifling Maine’s burgeoning clean energy industry. Maine needs investments in renewable energy projects with real environmental benefits, not a massive and harmful transmission corridor that lines CMP’s pockets.
NRCM News Releases, Statements, & Op-eds:
- Judge Denies CMP's Motion to Delay New Law Terminating CMP Corridor December 16, 2021
- Maine DEP Suspends CMP Corridor Permit November 23, 2021
- Mainers Rally at DEP HQ to Call for Immediate Suspension of Permit for CMP Corridor November 18, 2021
- New Poll: Maine Voters Want CMP to Stop Corridor Cutting, Support DEP Suspending Permit November 17, 2021
- Mainers Demand CMP Corridor be Terminated — Read NRCM's statement after November 2nd election results November 2, 2021
- Conservation Groups Move to Add U.S. Department of Energy to CMP Corridor Lawsuit March 29, 2021
- Hydro-Quebec Exploiting Legal Loophole to Influence Maine Voters March 15, 2021
- Mainers Deserve Thorough, Open Review of CMP Corridor February 2, 2021 (Portland Press Herald op-ed by NRCM CEO Lisa Pohlmann, Appalachian Mountain Club President John Judge, and Chapter Director of Sierra Club Maine Sarah Leighton)
- What's at Risk: Photo Essay of the Lands the CMP Corridor Would Destroy January 25, 2021 (by guest blogger Sam Steele)
- Groups File for Injunction to Halt CMP's Premature Plans to Begin Corridor Work November 12, 2020
- Environmental Groups File Lawsuit Challenging Army Corps for Indefensible CMP Corridor Analysis October 28, 2020
- US Army Corps & Dept. of Energy Identify Major Issues with CMP Corridor August 13, 2020
- Hydro-Quebec Dramatically Escalates Campaign to Influence Maine Elections July 30, 2020
- CMP & Hydro-Quebec Have Spent Record-breaking $16.78M on Campaign for the CMP Corridor July 7, 2020
- Citing Irreparable Harm to Maine's Environment, NRCM Appeals DEP Permit for CMP Corridor June 10, 2020
- NRCM Statement on DEP Permit for Controversial CMP Corridor Proposal May 11, 2020
- CMP and Hydro-Quebec Have Spent an Astounding $9 Million on Desperate Campaign to Save CMP Corridor April 13, 2020
- Leading Maine Conservation Groups Criticize DEP's Draft Permit on Controversial CMP Corridor March 13, 2020
- CMP Spends a Staggering $2.3M in 3 Months on Campaign to Boost Controversial Corridor January 16, 2020
- LUPC decision on CMP Corridor Ignores Harm Done to Maine January 8, 2020
- Mainers Call for Fairness in Army Corps Review of CMP Corridor December 5, 2019
- Congressman Golden Calls for a Public Hearing on the Army Corps Review of CMP Transmission Corridor October 16, 2019
- Six More Maine Towns and Two Major Unions Vote Overwhelmingly to Oppose CMP Corridor June 28, 2019
- U.S. EPA Says CMP's Permit Application to the U.S. Army Corps of Engineers is Incomplete May 3, 2019
- Statewide Poll Shows Strong Opposition to CMP Corridor April 1, 2019
- CMP “Settlement” Less Than Meets the Eye, Opposition to Corridor Continues to Grow Feb. 20, 2019
- Maine DEP Calls CMP’s Transmission Line Application “Insufficient” and “Incomplete” – CMP Timeline Delayed Even More Nov. 5, 2018
- PUC Delays CMP Power Line Hearings, Per Request by NRCM, Others Oct. 26, 2018
- Mainers Overwhelmingly Oppose CMP Transmission Line Oct. 18, 2018
- "New Study Shows CMP Transmission Project Would Not Reduce Climate-changing Carbon Pollution" Oct. 17, 2018
- NRCM June 2018 Statement: CMP has Not Demonstrated Climate Benefits for Transmission Project
- NRCM testimony at August 2018 Massachusetts DPU hearing
- NRCM statement in opposition to proposed CMP transmission line Feb. 21, 2018
Background Materials on CMP Corridor Proposal
- Brattle Group study
- ESAI Power study
- CMP’s Site Location of Development application here.
- View Filings in the Public Utilities Commission proceeding 2017-00232 here.
- Detailed CMP transmission line map of the proposed route from Canada to Lewiston
On February 21, 2019, CMP submitted a proposed settlement agreement to the Public Utilities Commission (PUC). In our comments in opposition to the proposed settlement agreement we explain how the proposed settlement agreement doesn’t address any of our primary concerns about this project.
Banner photo: The view from Sally Mountain over Attean Pond by J.Monkman/NRCM